Construction Manager: DeMaria Building Company
The scope work for this project includes:
Project began in 2013 and was completed in 2017.
Mass grading to reconstruct discharge pond banks.
Construct new perimeter roads.
Mass grading to construct new ash landfill.
Installation of new drainage piping.
Construct new swales.
Provide and install fabric and limestone sand for the ash landfill.