General Contractor: Gilbane/Clark Joint Venture
Contract Amount: $ 4,750,000
The scope work for this project includes:
Demolition of asphalt parking, concrete curbs, islands, and trees
Underground utility removals
Installation of a beam and wood lagging earth retention system up to 50 feet deep
Mass excavation of over 125,000 cubic yards
Excavate and backfill for building foundations, mechanical and electrical